Waitohi: Picton Ferry Precinct Redevelopment
KiwiRail / Port Marlborough · Marlborough
Redevelopment of the Picton ferry precinct (Waitohi) for the new rail-enabled Cook Strait ferries: a new terminal building, wharf and linkspan, a Dublin Street overbridge, and improved links between the precinct and town. Physical works, including demolition of the old vehicle access bridge, began in early 2026. The South Island portside half of the ~$1.86b Interislander ferry programme.
Data current as at 13 Jun 2026, when the pipeline was last checked against its source.
Key facts
- Region
- Marlborough
- Sector
- Transport
- Status
- Under Construction
- Estimated value
- $400m
- Indicative completion
- 2029
- Funding status
- Fully Funded
- Lead organisation
- KiwiRail / Port Marlborough
- Election risk
- Low
Election risk assessment
The South Island side of the Cook Strait ferry replacement. Port infrastructure agreements are signed within the fixed $1.86B programme; committed and under construction.
Government priority alignment
HIGH: Critical inter-island freight and passenger link, core land-transport resilience.
Chronology
- 2022Waitohi ferry precinct redevelopment confirmed (~$360m terminal)
- 2024Replanned alongside the new Cook Strait ferry procurement
- 2026Physical works begin: old vehicle access bridge demolished
- 2029Terminal ready for the new rail-enabled ferries