Waikato Water Supply Programme

Watercare Services (Auckland Council) / Waikato-Tainui alliance · Waikato

A new raw water intake on the Waikato River, a 50km pipeline, a 50-megalitre reservoir at Pukekohe West and a new treatment plant, lifting treated supply to Auckland from 200 to 300 million litres a day by the end of 2033. Watercare is procuring an alliance to deliver it, with construction from 2028. It sits inside Watercare's $15.2b programme, but the $1.7b here is its own published figure.

80
Strongest delivery signals Data: High
Delivery Confidence Score, 0 to 100, higher is better: a ranking of how strong this project's delivery signals are, not a probability. It blends eight factors, including the election risk and policy alignment shown below.
Breakdown▾

Data current as at 16 Sept 2026, when the pipeline was last checked against its source.

Key facts

Region
Waikato
Sector
Water
Status
Planning
Estimated value
$1.7b
Indicative completion
2033
Funding status
Fully Funded
Lead organisation
Watercare Services (Auckland Council) / Waikato-Tainui alliance
Election risk
Safe

Election risk assessment

Funded from water charges through Watercare's approved capital programme rather than Crown appropriation, so it does not depend on a government funding decision to proceed.

Government priority alignment

HIGH: Water security and the catch-up on water renewals are stated national priorities, and the work is ratepayer and charge funded rather than dependent on a Crown decision.

Recent changes

Chronology

Source

Watercare's $15.2b plan to bring more water from Waikato (NZ Herald, Jul 2026) ↗ · Auckland water bills to rise as Watercare unveils $15.2b programme (1News, 30 Jul 2026) ↗