Takitimu North Link Stage 1: Tauranga to Te Puna
NZ Transport Agency Waka Kotahi · Bay of Plenty
A 6.8km four-lane expressway from SH29 Takitimu Drive, Tauranga, to SH2 west of Te Puna, taking freight pressure off SH2 from the Port of Tauranga. Renamed from Tauranga Northern Link in September 2020 by NZTA with its six hapu Treaty partners. Stage 1 of a 14km corridor; Stage 2 to Omokoroa (about 7.7km) was fast-track approved in March 2026 but has no construction funding. The $933m shown is the NZ Upgrade Programme allocation for the whole link, not a Stage 1 figure. Tolled from opening.
Data current as at 13 Jun 2026, when the pipeline was last checked against its source.
Key facts
- Region
- Bay of Plenty
- Sector
- Transport
- Status
- Under Construction
- Estimated value
- $933m
- Indicative completion
- 2028
- Funding status
- Fully Funded
- Lead organisation
- NZ Transport Agency Waka Kotahi
- Election risk
- Low
Election risk assessment
Under construction with committed funding. Road of National Significance.
Government priority alignment
HIGH: RoNS freight route serving the Port of Tauranga, a strong policy fit.
Chronology
- 2015Tauranga Northern Link first scoped as part of Bay of Plenty transport strategy
- 2019Business case approved; route designation confirmed through Te Puna Valley
- 2020Crown commits funding. Procurement process begins. Renamed Takitimu North Link (3 September) by NZTA with its six hapū Treaty partners
- 2021Stage 1 construction begins
- 2024Completion pushed from 2026 to 2027 at the earliest (February), an estimate since superseded
- 2026Stage 1 major structures largely complete, all bridge construction scheduled to finish this year. Stage 2 (Te Puna to Ōmokoroa) granted all statutory approvals by fast-track on 19 March, construction funding still awaiting availability
- 2028Stage 1 due for completion, opening tolled to freight and general traffic
Source
NZTA: Takitimu North Link ↗ · Beehive: Takitimu North Link Stage 2 fast-tracked (Mar 2026) ↗ · Beehive: Milestone reached for Takitimu North Link Stage 1 (Feb 2025) ↗