SH1 Papakura to Drury Upgrade
NZ Transport Agency Waka Kotahi · Auckland
A $423m NZ Upgrade Programme widening of SH1 to three lanes each way over about 6km from Papakura to Drury South, with rebuilt Papakura and Drury interchanges, wide shoulders for future buses and a shared path. Alongside it KiwiRail has added three stations: Drury and Paerata opened on 2 August 2026, the first passenger services there since 1972, and Ngakoroa is under construction for 2027.
Data current as at 13 Jun 2026, when the pipeline was last checked against its source.
Key facts
- Region
- Auckland
- Sector
- Transport
- Status
- Under Construction
- Estimated value
- $423m
- Indicative completion
- 2027
- Funding status
- Fully Funded
- Lead organisation
- NZ Transport Agency Waka Kotahi
- Election risk
- Low
Election risk assessment
NZ Upgrade Programme project, fully funded and well under construction, low political risk.
Government priority alignment
HIGH: Growth and freight corridor upgrade with public-transport provision.
Chronology
- 2020Funded under the NZ Upgrade Programme
- 2023Construction under way
- 2026Drury and Paerātā stations opened (2 August); Ngākōroa station targeted 2027; motorway widening progressing
- 2026Drury and Paerata railway stations open on the Southern Line (2 August), the first passenger services there since 1972
Source
NZTA ↗ · Auckland Transport: new Drury and Paerata railway stations open ↗