Ruakākā Energy Park: Battery & Solar
Meridian Energy (NZX-listed, majority state-owned) · Northland
Meridian's energy park at Ruakākā, south of Marsden Point: a 100MW grid-scale battery with two hours of storage, completed in May 2025, and a 130MW solar farm under construction from August 2025. The $413m shown is the sum of the two published figures, $186m for the battery and $227m for the solar farm, not a single park total.
Data current as at 16 Sept 2026, when the pipeline was last checked against its source.
Key facts
- Region
- Northland
- Sector
- Energy
- Status
- Under Construction
- Estimated value
- $413m
- Indicative completion
- 2027
- Funding status
- Fully Funded
- Lead organisation
- Meridian Energy (NZX-listed, majority state-owned)
- Election risk
- Safe
Election risk assessment
Commercial renewable investment by Meridian, under construction and not dependent on government funding.
Government priority alignment
HIGH: Grid-scale renewable generation and storage supporting the electricity transition.
Recent changes
- 2026-W37Major New project added: Ruakākā Energy Park: Battery & Solar (Under Construction, $413m).
Chronology
- 2023Consents secured; final investment decision on the battery
- 2025100MW battery commissioned; solar farm construction begins
- 2027expectedSolar farm targeted for completion
Source
Meridian Energy ↗ · Meridian: completion of Ruakākā Battery Energy Storage System ↗ · Meridian: proceeding with the $227m Ruakākā solar farm ↗