NZ InfraWatch Open the live map →
ENERGY

Ruakākā Energy Park: Battery & Solar

Meridian Energy (NZX-listed, majority state-owned) · Northland

Meridian's energy park at Ruakākā, just south of Marsden Point. A 100MW grid-scale battery (commissioned 2025) plus a ~130MW solar farm under construction, together firming Northland supply and the upper North Island grid. Estimated ~$480m across both stages (indicative).

97
Strongest delivery signals Data: High
Delivery Confidence Score, 0 to 100, higher is better: a ranking of how strong this project's delivery signals are, not a probability. It blends eight factors, including the election risk and policy alignment shown below.
Breakdown

Data current as at 13 Jun 2026, when the pipeline was last checked against its source.

Key facts

Region
Northland
Sector
Energy
Status
Under Construction
Estimated value
$480m
Indicative completion
2027
Funding status
Fully Funded
Lead organisation
Meridian Energy (NZX-listed, majority state-owned)
Election risk
Safe

Election risk assessment

Commercial renewable investment by Meridian, under construction and not dependent on government funding.

Government priority alignment

HIGH: Grid-scale renewable generation and storage supporting the electricity transition.

Chronology

Source

Meridian Energy ↗