Renewable Energy: Wind Farms (National)
Meridian, Contact, Genesis, Mercury (NZX-listed gentailers) · National / Multi-region
Grid-scale wind built by the listed gentailers, tracked as a portfolio rather than one scheme. Operating: West Wind (142.6MW), Turitea (222MW), Harapaki (176MW, $448m) and Kaiwera Downs, which reached its full 198MW across 46 turbines when Mercury opened Stage 2 in September 2026, making it the South Island's largest. Stage 2 added 36 turbines and 155MW for $486m. The gentailer builds still under way are tracked here as their own entries: Kaiwaikawe and Mahinerangi Stage 2. The NZ Wind Energy Association counts 1,265MW operating across 21 farms at December 2025.
Data current as at 16 Sept 2026, when the pipeline was last checked against its source.
Key facts
- Region
- National / Multi-region
- Sector
- Energy
- Status
- Under Construction
- Estimated value
- Value TBC
- Indicative completion
- TBC
- Funding status
- Fully Funded
- Lead organisation
- Meridian, Contact, Genesis, Mercury (NZX-listed gentailers)
- Election risk
- Safe
Election risk assessment
Market-driven renewable energy investment. Commercially funded. Fast RMA consent pathway exists.
Government priority alignment
HIGH: Fast-tracked renewable generation, a strong government energy priority.
Recent changes
- 2026-W37Info Owner: Various (Meridian, Contact, Genesis, Mercury) → Meridian, Contact, Genesis, Mercury (NZX-listed gentailers).
Chronology
- 2009WestWind (142MW, Makara Wellington) opens: NZ's largest wind farm at the time
- 2018Turitea Wind Farm (Manawatū, 222MW) consented after long legal process
- 2020Harapaki Wind Farm (Hawke's Bay, 176MW) resource consent granted
- 2021Turitea construction begins
- 2023Turitea fully operational (222MW, Mercury)
- 2024Harapaki operational (176MW, Hawke's Bay, Meridian). Kaiwera Downs Phase 2 in construction (155MW, Mercury)
- 2025Contact's ~380MW Southland (Slopedown) wind farm declined in March. NZ Wind Energy Association counts 1,265MW of operating onshore wind across 21 farms at December
- 2026Contact's Southland wind farm approved under the Fast-track Approvals Act (April); no final investment decision taken
- 2026Mercury opens Kaiwera Downs Stage 2 (9 September), taking the farm to 198MW across 46 turbines and about 675GWh a year. Stage 1 had been commissioned in November 2023
Source
Meridian Energy: West Wind ↗ · Meridian Energy: Harapaki ↗ · Mercury: Turitea Wind Farm ↗ · Mercury: Kaiwera Downs Wind Farm ↗ · NZ Wind Energy Association: operating onshore wind farms ↗ · NZ Wind Energy Association: onshore wind farm pipeline ↗