Mahinerangi Wind Farm Stage 2 (Puke Kapo Hau)
Mercury NZ (NZX-listed, majority state-owned) · Otago
Stage 2 of the Mahinerangi wind farm west of Dunedin (Stage 1, 36MW, commissioned 2011), gifted the name Puke Kapo Hau. Up to 44 modern turbines, down from an earlier 100-turbine consent, plus a 110kV line, a substation and a 60MW battery, for up to 190MW installed. Fast-track approved on 3 July 2026, the sixth renewable energy project through that process. Construction still needs Mercury board approval. Estimated ~$550m (indicative).
Data current as at 13 Jun 2026, when the pipeline was last checked against its source.
Key facts
- Region
- Otago
- Sector
- Energy
- Status
- Planning
- Estimated value
- $550m
- Indicative completion
- 2030
- Funding status
- No Source
- Lead organisation
- Mercury NZ (NZX-listed, majority state-owned)
- Election risk
- Safe
Election risk assessment
Commercial renewable investment, broadly bipartisan. Fast-track approval granted July 2026; construction is not yet board-approved, so timing is uncertain.
Government priority alignment
HIGH: New wind generation supporting the renewable-electricity transition.
Chronology
- 2011Stage 1 (36MW) commissioned
- 2025Fast-track application lodged for the Stage 2 expansion
- 2026Expert panel issues draft decision and conditions (June)
- 2026Fast-track approval granted (3 July); construction subject to Mercury board approval
Source
Mercury ↗ · Fast-track Approvals: Mahinerangi Wind Farm ↗ · Beehive: Sixth renewable energy project fast-tracked (3 Jul 2026) ↗