NZ InfraWatch Open the live map →
ENERGY

Haldon Solar Farm: Mackenzie Basin

Lodestone Energy (private developer) · Canterbury

A 220MW solar farm on 320 hectares within Haldon Station in the Mackenzie Basin, generating about 370GWh a year, enough for roughly 45,000 homes. Cost is put at about $310m and the build at 12 to 16 months. It is the first solar farm approved under the Fast-track Approvals Act. The Environmental Defence Society has appealed to the High Court.

42
Weak signals: elevated risk Data: High
Delivery Confidence Score, 0 to 100, higher is better: a ranking of how strong this project's delivery signals are, not a probability. It blends eight factors, including the election risk and policy alignment shown below.
Breakdown▾

Data current as at 16 Sept 2026, when the pipeline was last checked against its source.

Key facts

Region
Canterbury
Sector
Energy
Status
Planning
Estimated value
$310m
Indicative completion
TBC
Funding status
No Source
Lead organisation
Lodestone Energy (private developer)
Election risk
Extreme

Election risk assessment

Privately developed renewable generation, not dependent on a Crown funding decision. The live risk here is legal rather than political: the Environmental Defence Society has appealed the fast-track approval to the High Court.

Government priority alignment

HIGH: Renewable generation and fast-track consenting are both stated government priorities; this is the first solar farm approved under the Act.

Recent changes

Chronology

Source

Lodestone's Haldon Solar Farm wins fast-track approval in Mackenzie Basin (NZ Herald) ↗ · Mackenzie Country Solar Farm Should Have Been Declined, Says EDS (Scoop, 4 Sep 2026) ↗ · Haldon Station Solar Farm Project Enters Fast Track (Lodestone Energy) ↗

View Haldon Solar Farm: Mackenzie Basin on the live map →