A solar farm across about 400 hectares at Foxton, developed by Genesis Energy. Genesis puts it at 220MWp and roughly 345 GWh a year, enough for about 47,000 homes. Granted fast-track approvals subject to conditions on 14 August 2026, the eighth renewable energy project approved under the Act. Genesis has not published a build cost or a construction start date.
Data current as at 16 Sept 2026, when the pipeline was last checked against its source.
Key facts
- Region
- Manawatū-Whanganui
- Sector
- Energy
- Status
- Planning
- Estimated value
- Value TBC
- Indicative completion
- TBC
- Funding status
- No Source
- Lead organisation
- Genesis Energy
- Election risk
- Safe
Election risk assessment
Commercially developed renewable generation with approvals already granted, so it does not depend on a government funding decision.
Government priority alignment
HIGH: Large-scale solar generation supporting the renewable-electricity transition.
Recent changes
- 2026-W37Major New project added: Foxton Solar Farm (Planning, value TBC).
Chronology
- 2026Substantive application lodged by Genesis Energy under the Fast-track Approvals Act (23 February) and deemed complete on 16 March
- 2026Found to have no competing applications (30 March); expert panel appointed and decision timeframe set by the convener (24 April)
- 2026Expert panel grants approvals subject to conditions (14 August): a solar farm across about 400 hectares connecting to the national grid
Source
Fast-track Approvals: Foxton Solar Farm ↗ · Fast-track Approvals: Foxton Solar Farm, the decision ↗ · Beehive: Foxton Solar Farm fast-tracked ↗