NZ InfraWatch Open the live map →
MINING

Bendigo-Ophir Gold Project

Santana Minerals · Otago

Proposed open-pit and underground gold mine at Bendigo, Central Otago, targeting about 120,000 ounces a year over a 30-year permit. Capital cost around A$277m (NZ~$300m). Consented via the Fast-track Approvals Act with a decision due in October 2026; capital raising underway. Controversial locally.

58
Mixed signals Data: Medium
Delivery Confidence Score, 0 to 100, higher is better: a ranking of how strong this project's delivery signals are, not a probability. It blends eight factors, including the election risk and policy alignment shown below.
Breakdown

Data current as at 13 Jun 2026, when the pipeline was last checked against its source.

Key facts

Region
Otago
Sector
Mining
Status
Planning
Estimated value
$300m
Indicative completion
2027
Funding status
Part Funded
Lead organisation
Santana Minerals
Election risk
High

Election risk assessment

Prospective open-pit and underground gold mine in Central Otago, consented through the Fast-track Approvals Act. A coalition flagship for the minerals strategy, but new large-scale mining is opposed by Labour and the Greens, and the project is not yet built.

Government priority alignment

HIGH: Central to the government minerals strategy (double minerals exports by 2035) and the Fast-track regime.

Source

Fast-track: Bendigo-Ophir Gold Project ↗ · Beehive: Major Fast-track mining project approved ↗

View Bendigo-Ophir Gold Project on the live map →